A note from ATCO:

To ensure continued safe and reliable natural gas service to customers, ATCO Gas is installing a natural gas line in your neighbourhood.

Project details:

  •         ATCO Gas is installing a natural gas line along 121 Street from 102 Avenue to 106 Avenue. The combination of 323mm/12in and 406mm/16in steel pipe will be approximately .75km/.5mi in length
  •         Installation is scheduled to begin around January 18, 2016 and will be complete around February 29, 2016, weather permitting.

Potential impacts:

For the duration of the project, there will be closures as follows:

  •         The bike lane on 121 Street from 102 Avenue to 104 Avenue
  •         The parking lane on 121 Street from 104 Avenue to 106 Avenue
  •         The bike and walking trail at the north end of 106 Ave and east of 121 Street
  •         Partial sidewalk closure on 121 Street between 102 and 103 Avenue

Robert B. Somerville Co. Limited (Somerville) has been contracted by ATCO Gas to complete this portion of the work. You may receive or have received more detailed information regarding the work scheduled to take place.

While in the vicinity of your property, Somerville’s work will consist of digging on the roadways and/or boulevards in your neighbourhood. Excavations open and accessible to the public will be supervised by a Somerville representative. If unsupervised, the site will be fenced and/or barricaded to help ensure public safety. Please be aware of these hazards and avoid excavation sites.

ATCO Gas is completing this work as part of ATCO Pipelines’ Urban Pipeline Replacement (UPR) Program, which involves replacing and relocating vintage high-pressure pipelines in Calgary and Edmonton primarily into the Transportation/ Utility Corridors surrounding both cities. 

ATCO Gas thanks you for your cooperation and we will make every effort to minimize any inconvenience. We will complete our work in a safe, efficient manner and restore the work area to the same condition as it was before the start of the project.

Questions?  Visit http://www.atcopipelines.com/upr/

 